IPS 2024-1218 County of Essex – Essex Civic Centre Interior Renovations Phase 3 – committee Rooms Addenum #1, #2, #3, #4, #5, #6, #7

Closing Date: January 21, 2025 1:00 pm
Location: 360 Fairview Ave W, Essex, ON N8M 1Y3

The scope of this project is to complete the demolition and interior renovations of a portion of the existing area of the Second Floor area which currently contain the former Warden’s Office  suite, a number of existing large meeting rooms, men’s and women’s washrooms and small area of existing offices in the southeast corner of the second floor. Abatement of the entire scope of work area is to be included as part of this base bid with all identified materials listed in the provided DSS report (in tender documents) to be removed and disposed of. All existing construction will be required to be removed and replaced with new including all mechanical and electrical work as indicated on the tender drawings. New flooring, ceilings, wall partitions, interior doors and washroom fixtures are required throughout the renovated area as shown on the drawings. Existing hoarding that the Owner has stored on site from previous renovations is to be erected as shown on the tender demolition drawings by the successful bidder’s forces around the scope of work area. The general contractor will need to take a phased approach to complete the entire scope of work as access will be required to be maintained to the suite across the corridor (Corridor – Rm. 221 on architectural floor plans) throughout the construction period. The majority of the scope of work can be completed with this entire Corridor hoarded off with the exception being the northmost end which is to have the hoarding erected so access to the suite across the corridor (ERCA occupied suite) can have access through the door towards at the north end. This part of the corridor can then be completed (flooring, drywall, sliding door installation, electrical, etc.) when the rest of the corridor is completed and access to the ERCA suite can be provided from the south stair entry point. This situation should be considered in terms of cost and timing by the General Contractor with their base bid submissions. Another condition Bidders should be aware of is that the service elevator in the building does not extend to the second floor. Large items or materials needed to be take to the second floor scope of work area will need to be manually carried to the second floor by way of the south stair (entry) (which will be dedicated as a Contractor’s Access point for this work) or the Contractor could use lift machinery outside of the building to lift materials to an exterior window location in the scope of work area, carefully remove the glazing unit and move material through the improvised opening. Any labour, equipment or material costs potentially associated with moving material to the second
floor for this work is to be accounted for by bidders and included in their base bid pricing.

Addendum #1 dated Jan. 02/25

Addendum #2 dated Jan. 03/25

Addendum #3 dated Jan. 07/25

Addendum #4  dated Jan. 09/25

Addendum #5 dated Jan. 15/25

Addendum #6 dated Jan. 16/25

Addendum #6 dated Jan. 17/25

This field is for validation purposes and should be left unchanged.

The scope of this project is to complete the demolition and interior renovations of a portion of the existing area of the Second Floor area which currently contain the former Warden’s Office  suite, a number of existing large meeting rooms, men’s and women’s washrooms and small area of existing offices in the southeast corner of the second floor. Abatement of the entire scope of work area is to be included as part of this base bid with all identified materials listed in the provided DSS report (in tender documents) to be removed and disposed of. All existing construction will be required to be removed and replaced with new including all mechanical and electrical work as indicated on the tender drawings. New flooring, ceilings, wall partitions, interior doors and washroom fixtures are required throughout the renovated area as shown on the drawings. Existing hoarding that the Owner has stored on site from previous renovations is to be erected as shown on the tender demolition drawings by the successful bidder’s forces around the scope of work area. The general contractor will need to take a phased approach to complete the entire scope of work as access will be required to be maintained to the suite across the corridor (Corridor – Rm. 221 on architectural floor plans) throughout the construction period. The majority of the scope of work can be completed with this entire Corridor hoarded off with the exception being the northmost end which is to have the hoarding erected so access to the suite across the corridor (ERCA occupied suite) can have access through the door towards at the north end. This part of the corridor can then be completed (flooring, drywall, sliding door installation, electrical, etc.) when the rest of the corridor is completed and access to the ERCA suite can be provided from the south stair entry point. This situation should be considered in terms of cost and timing by the General Contractor with their base bid submissions. Another condition Bidders should be aware of is that the service elevator in the building does not extend to the second floor. Large items or materials needed to be take to the second floor scope of work area will need to be manually carried to the second floor by way of the south stair (entry) (which will be dedicated as a Contractor’s Access point for this work) or the Contractor could use lift machinery outside of the building to lift materials to an exterior window location in the scope of work area, carefully remove the glazing unit and move material through the improvised opening. Any labour, equipment or material costs potentially associated with moving material to the second
floor for this work is to be accounted for by bidders and included in their base bid pricing.

Addendum #1 dated Jan. 02/25

Addendum #2 dated Jan. 03/25

Addendum #3 dated Jan. 07/25

Addendum #4  dated Jan. 09/25

Addendum #5 dated Jan. 15/25

Addendum #6 dated Jan. 16/25

Addendum #6 dated Jan. 17/25

YOU MAY ALSO BE INTERESTED IN...

International Student Centre 2025 Move Adendum #1, #2, #3

The Work is identified as the International Student Centre 2025 Move located at the Joyce
Entrepreneurship Centre, University of Windsor, Windsor, Ontario, also known as Project No.:
003050, as prepared by Tandem Engineering Group, 1880 Assumption St. Windsor ON. In general the
scope of work includes but is not limited to, dismantling and relocation of existing modular walls and
frame assemblies, provision of new office spaces including new drywall construction, patch and painting,
new doors, new window, new hardware, relocation of a fire alarm device, relocation of lighting switches

Addendum #1 Dated Jan. 17/25

Addendum #2 Dated Jan. 17/25

Addendum #3 Dated Jan. 27/25

LCBO Store # 371Exterior Upgrades

This Request for Quotation (the “RFQ”) is an invitation by the LCBO to prospective bidders to submit a bid to supply construction labour and materials for exterior upgrade with minor interior painting at existing LCBO store 371, in Mississauga, Ontario with an approximate square footage of 11,500 as per enclosed drawings and specifications.

Estimated Project start date: To be determined with the selected bidder.

Estimated Project end date: March 31, 2025.

TCI Titan Website Update – 05/15/2024

Website Update – Users must update their trades and categories to get relevant notifications for bids

True Phantom Solutions (TPS) Renovations And Addition Addendum #1, #2, #3

The intent of the bid call is to obtain an offer to preform work to complete “TPS Renovations and Addition in Tecumseh, Ontario as indicated in the bid documents prepared by Passa Associates Inc. Architects and identified as Project No. 2699.   The project consists of the renovation to the existing 1-storey (approx 6,00 sq. ft.) structure and a small 1-storey addition (approx. 245 sq. ft.) on the East side of the structure.

Please provide a lead letter 24hrs in advance of the tender closing to confirm your scope of work.

Addendum #1 dated Jan. 20/25

Addendum #2 dated Jan. 24/25

Addendum #3 dated Jan. 29/25

University of Windsor 2025-01-06 California Residence – Addendum #1, #2

The University of Windsor is inviting pre-qualifications and quotations proposals from General
Contractors for a Student Residence. The building is a 3 Storey 3D printed building of
approximately 1,250 sm (13,400 sf) is intended to have the excavation and construction started in
early March 2025 and be completed by early December 2025 for occupancy in early January 2026.
During the deficiency correction period in late November 2025 the University will be installing
window blinds and furniture outside of this construction contract. General Contractors must be pre-qualified
as per the technical criteria set forth herein prior to accepting their bid price.

Construction start March 01/25 Substantial completion Nov. 30/25

Addendum #1 dated Jan. 8/25

Addendum #2 dated Jan. 14/25