International Student Centre 2025 Move Adendum #1, #2, #3

Closing Date: January 29, 2025 2:00 pm
Location: 401 Sunset Avenue, Windsor, ON. N9B 3P4

The Work is identified as the International Student Centre 2025 Move located at the Joyce
Entrepreneurship Centre, University of Windsor, Windsor, Ontario, also known as Project No.:
003050, as prepared by Tandem Engineering Group, 1880 Assumption St. Windsor ON. In general the
scope of work includes but is not limited to, dismantling and relocation of existing modular walls and
frame assemblies, provision of new office spaces including new drywall construction, patch and painting,
new doors, new window, new hardware, relocation of a fire alarm device, relocation of lighting switches

Addendum #1 Dated Jan. 17/25

Addendum #2 Dated Jan. 17/25

Addendum #3 Dated Jan. 27/25

This field is for validation purposes and should be left unchanged.

The Work is identified as the International Student Centre 2025 Move located at the Joyce
Entrepreneurship Centre, University of Windsor, Windsor, Ontario, also known as Project No.:
003050, as prepared by Tandem Engineering Group, 1880 Assumption St. Windsor ON. In general the
scope of work includes but is not limited to, dismantling and relocation of existing modular walls and
frame assemblies, provision of new office spaces including new drywall construction, patch and painting,
new doors, new window, new hardware, relocation of a fire alarm device, relocation of lighting switches

Addendum #1 Dated Jan. 17/25

Addendum #2 Dated Jan. 17/25

Addendum #3 Dated Jan. 27/25

YOU MAY ALSO BE INTERESTED IN...

LCBO Store # 371Exterior Upgrades

This Request for Quotation (the “RFQ”) is an invitation by the LCBO to prospective bidders to submit a bid to supply construction labour and materials for exterior upgrade with minor interior painting at existing LCBO store 371, in Mississauga, Ontario with an approximate square footage of 11,500 as per enclosed drawings and specifications.

Estimated Project start date: To be determined with the selected bidder.

Estimated Project end date: March 31, 2025.

Leddy Library West Graduate Student Lounge Interior Fit-Out Addendum #1, #2, #3

the Work is identified as the Leddy Library West Graduate Student Lounge Interior Fit-out located at Leddy Library West, University of Windsor, Ontario, also know as Project No.: HPA 2001.02, as prepared by the Consultant Hariri Pontarini.  In general the scope of work includes but is not limited to, the Graduate Student Lounge Interior Fit-out on the first Floor of Leddy Library West work as indicated.

Addendum #1 Dated January 22/25

Addendum #2 Dated January 23/25

Addendum #3 Dated January 24/25

Please note the Alternate pricing #1 See Addendum #3

Town of Tecumseh Lakewood Park Upgrades – Addendum #1, #2, #3

The Town of Tecumseh is seeking proposals from qualified and experienced Contractors to provide washroom building facility, splash pad, bocce court, gazebo, and surrounding hard surface area at  Lakewood Park, 13451 Riverside Dr. East. in the Town of Tecumseh. Work shall include associated appurtenances buildings, hard surfaces, sewer and drainage work watermain. The work to be carried out shall include the furnishing of all labour, supervision, plant and materials necessary to carry out the specifications described hereinafter or as may otherwise be directed by the Engineer for the project.

Addendum #1 – Jan. 6/25

Addendum #2 – Jan. 15/25

Addendum #3 – Jan. 15/25

University of Windsor 2025-01-06 California Residence – Addendum #1, #2

The University of Windsor is inviting pre-qualifications and quotations proposals from General
Contractors for a Student Residence. The building is a 3 Storey 3D printed building of
approximately 1,250 sm (13,400 sf) is intended to have the excavation and construction started in
early March 2025 and be completed by early December 2025 for occupancy in early January 2026.
During the deficiency correction period in late November 2025 the University will be installing
window blinds and furniture outside of this construction contract. General Contractors must be pre-qualified
as per the technical criteria set forth herein prior to accepting their bid price.

Construction start March 01/25 Substantial completion Nov. 30/25

Addendum #1 dated Jan. 8/25

Addendum #2 dated Jan. 14/25